T. W. King 30inch Water Supply Line to Pump Station #2


Created with flickr slideshow.

 

Project Information:

This Capital Improvement Program (CIP) project consists of the design and construction of a new 30" water supply line from Ft. Worth to Southlake's T. W. King pump station #2 located in the northern part of the City. This water supply line, broken into segments labeled A through F, will ensure the City is able to meet our projected water demands for 2025.

Freese and Nichols, Inc. will design the new 30" water supply pipeline to the T. W. King Pump Station #2. Segments A and F are common to both routes analyzed and therefore, were designed as part of the first phase of this project. Segment A begins at the intersection of Pearson Lane and Florence Rd., and continues to the east until Randol Mill Rd. (FM 1938). Segment F begins at the north side of the SH 114 and T. W. King intersection, and connects to the T. W. King Pump Station. The total scope of this portion of the project is approximately 7,500 linear feet of 30" diameter water transmission line.

 

Project Details:

Consultant: Freese and Nichols, Inc.

Contractor: Circle C Construction for Segments "A" and "F"

Cost: $ 10,136,000

Staff Contact: Cheryl Taylor, P.E., Civil Engineer, (817) 748-8100

 

View a More Detailed Map Here

 

 

T. W. King 30 inch Water Supply Line Segments A thru F:

 

  • T.W. King Water Supply Line Segment "A"
    • Along Florence Rd.
    • Waterline completed November 2009.
    • Pavement reconstruction currently underway.
  • T.W. King Water Supply Line Segment "B" 
    • From Florence to Randol Mill Bend
    • Design is 90% completed
    • Construction requires right of way acquisition, currently 30% completed.
  • T.W. King Water Supply Line Segment"C"
    • From Randol Mill Bend to Dove Rd.
    • Design is 90% completed
    • Construction requires an inter-local agreement and a license agreement with the City of Westlake
  • T.W. King Water Supply Line Segment "D" 
    • From Dove Rd. to SH114
    • Design is 90% completed
    • Construction requires an inter-local agreement and a license agreement with the City of Westlake
  • T.W. King Water Supply Line Segment "E" 
    • East Along SH114 to TW King
    • Design is 90% completed
    • Currently negotiating for an easement with the property owner
  • T.W. King Water Supply Line Segment"F" 
    • Along TW King Rd. to the new TW King Pump Station
    • Waterline completed January 2010.
    • Pavement reconstruction currently underway.