FM 1938 Water and Sewer Utility Relocation


Project Information



 As part of the FM 1938 Phase II Project, city utilities including city water lines and sewer lines will be relocated to accommodate construction along FM 1938. This is necessary to move existing utilities out from under the future wider roadway.

Project Details

Engineering Consultant:

Engineering cost shared with the City of Keller:
TranSystems

Engineering total: $328,500
  • Southlake's portion: $256,328.55
  • Keller's portion: $72,171.45
Construction Contractor:

Construction cost shared with the City of Keller:
Wison Contractor Services, LLC.

Construction total: $ 1,918,372.50
Start Date:
October 2013 (9 month project)
Anticipated Completion Date:
2016
Staff Contact:
Alex Ayala, P.E.
Title:
Civil Engineer
Phone Number:
(817) 748-8274