North Carroll Avenue

Project Background

This project will be completed in partnership with Tarrant County. This partnership is utilized once per year. The County provides assistance to the City for roadway projects. These projects help reduce the cost of roadway projects to the City. 

2021 Tarrant County ILA Project - North Carroll Avenue

This year's focus is going to be the North Carroll Avenue run from State Highway 114 to Burney Lane, to not include the Dove Road roundabout. The roundabout will remain open for the duration of the project. The project will completed in two phases comprised of three sectors. This project is scheduled to begin May 27, 2021 and will wrap up by August 6, 2021. The roadway will remain open for traffic with no lane closures for any extended period of time. Traffic control will consist mainly of flaggers to allow for north and southbound traffic.


Map of Sector A for the N. Carroll Repaving Project
  1. Zayne Huff

    Engineering Assistant
    Phone: (817)-748-8041

Phase I - As shown in the above map, this phase will consist of 2,500 linear feet of roadway beginning at Burney Lane and ending just north of the Dove roundabout. While work will begin on May 27th, the road will remain open and operational. Please note that during the project, that access to any given residence directly connected to North Carroll Avenue will be temporarily restricted. This restricted access will last no longer than one hour as the equipment completes work along the route. Affected residences will be notified one day prior to access restriction, weather permitting.

Map of Phase 2 N Carroll Ave Reconstruction

Phase II - As shown in the above map, this phase will consist of 3,750 linear feet of roadway beginning at just south of the Dove roundabout and ending at Whispering Lane. Work is scheduled to begin on June 18, weather permitting. The road will remain open and operational. Please note that during the project, that access to any given residence directly connected to North Carroll Avenue will be temporarily restricted. This restricted access will last no longer than one hour as the equipment completes work along the route. Affected residences will be notified one day prior to access restriction, weather permitting. 

Map of Phase 3 N Carroll Ave Reconstruction

Phase III - As shown in the above map, this phase is 3,100 linear feet and will start at Whispering Lane and end at SH 114. Work is scheduled to begin on July 1, weather permitting. The road will remain open and operational. Please note that during the project, that access to any given residence directly connected to North Carroll Avenue will be temporarily restricted. This restricted access will last no longer than one hour as the equipment completes work along the route. Affected residences will be notified one day prior to access restriction, weather permitting.