FM1938 Drainage Relief for Phase II

FM1938 Drainage Relief - Map

Project Information

This project will identify those areas and drainage structures that are in need of rehabilitation in order to alleviate reported flooding and potential flooding due to undersized culverts or inadequate drainage.

Project Details
Engineering Consultant: TranSystems
Construction Contractor: TBD
Current Budget: $250,000
Construction Start Date: 2015 (In conjunction with the roadway improvements)
Anticipated Completion Date: 2017
Southlake 2030 Comprehensive
Master Plan Item
:
MT14
Staff Contact: Alex Ayala, P.E.
Title: Civil Engineer
Phone Number: (817) 748-8274
For a more detailed description of this project, please see the "Public Works Capital Projects Update" quarterly report.